Multimedia:Project schedule
Appearance
- 13 - 18 October 2009
- Get started!
- Create workspace (Multimedia:Hub and linked pages)
- Start Preliminary user research
- Start Initial survey
- 19 - 25 October 2009
- Finish Initial survey
- Have Initial survey translated
- Put Initial survey & translations live
- Test Initial survey
- Put survey's CentralNotice & translations live
- Draft project schedule
- Prepare Ethnographic interviews
- 26 October 2009 - 1 November 2009
- Run Initial survey
- Prepare Meeting in Paris
- Start processing data from Initial survey
- 2 - 8 November 2009
- Process data from Initial survey
- Continue project planning
- Prioritize
- Prepare & attend Meeting in Paris
- 9 - 15 November 2009
- Get up-to-speed after the busy previous week
- Process data from Meeting in Paris
- Attend KDE imaging event
- 16 - 22 November
- Process data from Meeting in Paris
- Prioritize
- Process data from Initial survey (factor analysis)
- Plan, schedule & start running Ethnographic interviews
- 23 - 29 November
- Go to Paris for visa interview at the US embassy
- Continue to run Ethnographic interviews
- 30 November - 6 December
- Process data from Meeting in Paris
- Process data from Multimedia:Open forum
- Prioritize
- Do Domain research/Upload
- 7 - 13 December
- Move to SF
- Process data from Ethnographic interviews
- 14-20 December
- Process data from Ethnographic interviews
- Do Domain research/Upload
- Process data from Meeting in Paris
- Review UI for the add-media wizard
- Start Requirements definition
- 21-27 December
- Continue Requirements definition & prioritize
- Analyze & abstractify upload workflow
- End of December 2009
- Design upload workflow
- Design mockups for the upload interface
- Seek partners for Joint projects
- January - February 2010
- Develop first prototype
- Prepare Lab study 1
- Prepare 1st report? (perhaps after Lab study 1)
- Formalize Joint projects collaborations with partners
- March 2010
- Put 1st prototype live for Lab study 1
- Run Lab study 1
- Process data from Lab study 1
- Refine workflows & designs
- Prepare Wikimania submission
- April - September 2010
- Research, design, develop, test, refine
- Report
- Attend Wikimania
- October 2010
- Oct 8
- Code drop to protoype - backend revisions
- Oct 11
- Wikitech - documentation circulation
- Oct 15
- Code drop to protoype (frontend improvements)
- Blog posts / Village pump / Signpost to get community looking at prototype
- Oct 20
- Dark launch to live Commons
- Oct 22
- Code drop to protoype (more frontend)
- Oct 26
- Due to all-staff meetings, effectively the final working day October -- decide on release now or on Nov 1
- November
- Nov 1
- Launch on live Commons (if not before)
- Blog posts announcing launch
- Final reports
- Nov 5
- Tech blog post
- Code drop to prototype
- Nov 12
- Code drop to prototype
- Nov 15
- Bug fixes deployed to production
- Nov 19
- Code drop to protoype
- Nov 26
- Code drop to prototype
- Nov 29
- Bug fixes deployed to production